Veolia Facility Addition
Owner
Veolia North America
CONSTRUCTION MANAGER
Denham Blythe
MARKET
Industrial
LOCATION
Gum Springs, AR
Summary
This project was a 11,000 SF multilevel addition to an existing incineration facility. The tank farm consisted of a multilevel mat foundation, surrounded by a containment wall and containing a series of intermediate containment walls. Within the containment area, we placed several 20 ft and 30 ft octagon equipment pads. Throughout the structure, our crew installed pipe rack pedestals; pads for generators, transformers, radiation tanks, guard shacks, and more; and slabs on the bulk waste structure. We also installed a 65 ft+ truck scale with an approach and exit ramp.
Tons of Reinforcing
Cubic Yards of Concrete